The Guardian reports that David Gould, former chief operating officer at
the Defence Equipment and Support Organisation, stated in June 2007 that
AWE would build a new Trident warhead. At a defence industry conference
Mr Gould said: "The intention is to replace the entire Vanguard class
submarine system. Including the warhead and missile." The MoD continues
to deny that the government has taken the decision to build a new
warhead, despite the eight-year building project to modernise the
warhead manufacturing facility at AWE Aldermaston and Burghfield.
http://ukpress.google.com/article/ALeqM5jYnTLA2O1_zZeCJRPEMNLGYcqCAA