Nuclear Installations Inspectorate (NII)feedback to AWE Aldermaston emergency exercise May 1998

In response to FOI request by Rob Evans, Defence Procurement Agency provided the answer to the MoD question regarding NII feedback to the Aldermaston site emergency exercise at 13 May 1998. The performance of the situations control centre, health physics assessment room were deem to be good. Overall assessment of medical aspect was satisfactory. Emergency control point arrangements need to be fundamentally re-examined. Recommendations were made regarding on and off site activities and local response by facility and shift engineers.

By continuing to use the site, you agree to the use of cookies. More information

The cookie settings on this website are set to "allow cookies" to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click "Accept" below then you are consenting to this.

Close